My company has a license to K2 as we use the K2 system for other business lines. We first brought the idea up to our project management team, which confirmed that a process could be developed utilizing the K2 system to meet our needs. After we received the appropriate signoffs, a preliminary workflow chart was created, and we started having weekly meetings to
develop a workflow that worked for my team's needs and modified the workflow as necessary. After the workflow was developed that fit our needs, the testing phase is what we are currently in. We are currently performing an internal testing phase, and once all the issues are worked out, we will train our team in India and move the K2 process into production. We are projected to go live around May 15, 2024, which will start the collection of rent rolls and financial statements for
1Q2024.